Construction Update August 28

Regular Wednesday Construction Update Meeting Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Elevator lobby review of pathway and time frame.  Will likely end by Sept 9th at the latest Sewer lines are in and back filled and electrical is getting trenched.  Everything on is on time. Only possible slow down would be … READ MORE…

Construction Update August 21

Regular Wednesday Construction Update Meeting Site Logistics Plan review:  At Tom’s request, Greystar added detail to the section on elevator replacement.  Delivery of the elevator is expected on November 8, with installation to take 8 weeks, or until after the first week of January 2020.  There was discussion about the possibility of alternate routes for … READ MORE…

Construction Update August 14

Regular Wednesday Construction Update Meeting Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Similar to last week, except for when work is happening in the first floor elevator lobby. Rocky brought in a new dumpster for trash which is white and in the clergy parking lot. General info: Permit progress: The permits … READ MORE…

Construction Update August 7

Regular Wednesday Construction Update Meeting Site Logistics Plan review: Reviewed pathways and exits for upcoming work. NO changes this week General info: Permit progress: The permit could be in hand by tomorrow, it needs stamps and signatures. Once the permit is in hand: Sewer inspection Partial backfill in 6th Ave courtyard Increase the trenches to separate … READ MORE…

Construction Update August 1

Regular Wednesday Construction Update Meeting Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Breezeway pathway from 5th Ave Queen’s Courtyard will continue to be main entry to building. Olive St. parking lot will be available (the 2/3rds of the lot) again this week into next week. There are signs directing people to … READ MORE…

Construction Update July 24

Regular Wednesday Construction Updates  Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Breezeway pathway from 5th Ave Queen’s Courtyard will continue to be main entry to building.  New signs were installed for directions and advice that we have no ADA access currently. Olive St. parking lot will be available (the 2/3rds of the lot) … READ MORE…

Construction Update July 17

Regular Wednesday Construction Updates Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Breezeway pathway from 5th Ave Queen’s Courtyard will continue to be main entry to building.  New signs were installed for directions and advice that we have no ADA access currently. Olive St. parking lot will be available (the 2/3rds of the … READ MORE…

State of the Cathedral 2017

At the forum on Sunday, Dean Penny led us through a powerpoint presentation on the state of the Cathedral. Here’s the outline!  Good News: CAT Survey says we are healthy and spiritually vital Financial Accounts are in excellent shape Revenue and Expenses YTD in line with budget Recognized in the Community Outreach is growing Membership … READ MORE…