The Courtyard landscaping will be taken on by SPC, rather than engaging Greystar’s vendor. Kathleen & Bob are working with volunteer landscape architect, Robert Mayberry, on a plan for the greenery in the Courtyard. Resurfacing of the Queen’s Courtyard will progress this week: patching first, then resurfacing. There’s a fence across the courtyard so entry … READ MORE…

Courtyard chair lift will be installed by Thursday/Friday. Inspection comes in about two weeks. The installation has been completed as of 5/22/2020. Handrails for the steps are complete Samples for the finishes of the courtyard are TBD. Reviewed the first color test and were not happy with the brown color vs. red tone of the … READ MORE…

Rocky Update: Courtyard stairs are done. Kathleen will share photo with Tom. Handrails for it being fabricated Chairlift installer comes out again to inspect new housing and will then work out installation schedule, which will likely be a month out. Bids just shared for courtyard cement spruce-up via Brad to Tom. Tom will share with … READ MORE…

We hadn’t met in several weeks so had a catch-up meeting. Rocky Update: Dumpsites closed for a few days due to rain so dirt removal on hold a few days. They’re taking the down time to put a man lift in Stairs to the Queen’s Courtyard concrete was poured incorrectly so demo is happening this … READ MORE…

Reviewed status of Queen’s Courtyard work: More digging this week and concrete removal A/C unit out of Reception office and windows fixed Timing is on track (4 week expected time frame, one week done already) HVAC Status update: Ducting into Library and Receptionist office will be installed in the newly cored holes this week and … READ MORE…

Joe discussed the issues with the HVAC project: New route for the ducting figured out.  Using new ducting running from the new unit to the Library and Reception offices Duct will run into library from the new unit through the wall of the lobby and the library.  They are coring a 15” hole for 14” … READ MORE…

Meeting notes: Joe discussed the issues with the HVAC project: Followed up with BCM and fixed wiring issue Discussed and came up with solution for the receptionist and library offices: Take the hallway vents and enlarge them and refeed them into the two rooms with the issue Queen’s Courtyard demolition of the stairwell begins Monday … READ MORE…

Meeting Notes  Engineers will not sign off on working on the footings of the Stair 1 landing until other work has been completed. Rocky asks if it is possible to start the work for the Queen’s Courtyard instead while the back stairwell is on hold. Reviewed any potential conflicts with teams and did not find … READ MORE…

Meeting notes: Discussed the updates for HVAC: pipes are complete, electrical is not complete after all to the room controls, so more work needed before they can turn system on. Joe will be emailing a list of options for the contemplation of the future heating of the Cathedral Sanctuary and Great Hall and the fate … READ MORE…

Meeting notes: Discussed the updates for HVAC: pipes are complete, electrical is complete, pressure testing is complete, we see start up for the HVAC in the Great Hall Basement offices happening this week! Discussed Sacristy Brian Cox walk through from this morning: Need Bob to fire up the boiler to do some testing on flow.  … READ MORE…