Construction Update November 6

 Regular Construction Updates Meeting notes: Discussed the possibility of meeting weekly again.  Some communication was lost when we went to bi-weekly meetings.  We’ve decided due to schedules that we will meet on Tuesdays in the Fireside Room from 9:15-9:45a going forward. Temporary 2nd floor landing is being developed to get something out there and aid our … READ MORE…

Construction Update October 23

Regular Construction Updates Meeting notes: Switch over of power is still on for 10/24 pm to 10/25 am.  Rocky has their electrician on site at 9pm 10/24 and SDGE is expected to arrive, deenergize transformer to building.  They’ve pulled wires and they come back early a.m. to complete the work.  So when they “stab” the … READ MORE…

Construction Update October 9

Regular Construction Updates Meeting notes: Got the SDGE date Thursday 10/24/19 10 pm to 10/25/19 7am .  Greystar is good with us closing the offices for the 25th so they can do testing throughout both buildings. Elevator modification starts 10/21/19.  Should take 9 weeks, but we think it can be done quicker, closer to 7 weeks.  … READ MORE…

Construction Updates, October 2, 2019

Regular Wednesday Construction Update Meeting Date: Oct 2, 2019 Present: Meeting was canceled due to construction work on electrical system This week’s Top 5 points: TOP 5 to Communicate with Congregation: Electrical work is being done in anticipation of the “big switch over” who’s date is still TBD.  Phone and internet accessibility has been affected … READ MORE…

Construction Update September 25

Regular Construction Update Reviewed schedule: Title company said it’s ok to continue the demo work, so demo of the Admin building continues.  Tear down has begun. Working on coming up with a plan to protect the 2nd floor balcony walkway once demo really gets underway. Still waiting for Cox/ATT to bring their wiring over to the … READ MORE…

Construction Update September 18

Regular Construction Update Reviewed schedule: Queen’s Courtyard ready to begin demo Finishing stairs for thurifer porch and vesting stairwell by clergy lot SDGE releases received but questions about the address they have on the paperwork.  Greystar following up so there are no unexpected delays due to paperwork. Asbestos abatement done on Friday this week or … READ MORE…

Construction Update September 12

Regular Construction Update Meeting Reviewed schedule: SDGE looks like about 2 weeks left for main package underground. Asbestos abatement started in the Admin building this week. Cox conversion is progressing.  Cored holes on the north side of the workroom wall for entry point. They’ll run the lines once the main electrical is done. Tower bring … READ MORE…

Construction Update September 4

Regular Wednesday Construction Update Meeting Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Elevator lobby review of pathway and time frame.  Will likely end by Sept 9th at the latest Sewer lines are in and back filled and electrical is getting trenched.  Everything on is on time. Only possible slow down would be … READ MORE…

Construction Update August 28

Regular Wednesday Construction Update Meeting Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Elevator lobby review of pathway and time frame.  Will likely end by Sept 9th at the latest Sewer lines are in and back filled and electrical is getting trenched.  Everything on is on time. Only possible slow down would be … READ MORE…

Construction Update August 21

Regular Wednesday Construction Update Meeting Site Logistics Plan review:  At Tom’s request, Greystar added detail to the section on elevator replacement.  Delivery of the elevator is expected on November 8, with installation to take 8 weeks, or until after the first week of January 2020.  There was discussion about the possibility of alternate routes for … READ MORE…