Construction Update August 7

Regular Wednesday Construction Update Meeting Site Logistics Plan review: Reviewed pathways and exits for upcoming work. NO changes this week General info: Permit progress: The permit could be in hand by tomorrow, it needs stamps and signatures. Once the permit is in hand: Sewer inspection Partial backfill in 6th Ave courtyard Increase the trenches to separate … READ MORE…

2019 Second Quarter Statement

August 2, 2019 Dear St. Paul’s family, As usual, this quarter has been marked by lots of volunteers, lots of change, and many blessings coming from the hard work of innumerable individuals! Looking back, I deeply appreciate the contributions of our community to the consecration of our Bishop, Susan Brown Snook. It was a joyful … READ MORE…

Construction Update August 1

Regular Wednesday Construction Update Meeting Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Breezeway pathway from 5th Ave Queen’s Courtyard will continue to be main entry to building. Olive St. parking lot will be available (the 2/3rds of the lot) again this week into next week. There are signs directing people to … READ MORE…

Construction Update July 24

Regular Wednesday Construction Updates  Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Breezeway pathway from 5th Ave Queen’s Courtyard will continue to be main entry to building.  New signs were installed for directions and advice that we have no ADA access currently. Olive St. parking lot will be available (the 2/3rds of the lot) … READ MORE…

Construction Update July 17

Regular Wednesday Construction Updates Site Logistics Plan review: Reviewed pathways and exits for upcoming work. Breezeway pathway from 5th Ave Queen’s Courtyard will continue to be main entry to building.  New signs were installed for directions and advice that we have no ADA access currently. Olive St. parking lot will be available (the 2/3rds of the … READ MORE…

CCRP Update

Dear St. Paul’s family, You’ve probably started to notice some changes around our campus, such as a construction fence and the Porta-Potty in the Olive parking lot. They are signs that the real work of the Cathedral Campus Redevelopment Project is under way! Here’s a quick update: For the past several weeks repair work has … READ MORE…

BCP Introduction

Dear St. Paul’s family, A couple of weeks ago Chapter adopted a plan to move us to a balanced budget in 2020. You heard about the details at the Community Life Council meeting and in a letter I sent out to the congregation. Now we are beginning the process of implementing the plan, working into … READ MORE…