Construction Updates March 4

  • Reviewed status of Queen’s Courtyard work:
    • More digging this week and concrete removal
    • A/C unit out of Reception office and windows fixed
    • Timing is on track (4 week expected time frame, one week done already)
  • HVAC Status update:
    • Ducting into Library and Receptionist office will be installed in the newly cored holes this week and will complete by Thursday.
    • There will be hole patching
    • The electrical team from Blackhawk may need to come back to fix the connection to the J box that got moved.
  • Kathleen advised about the break in of 2/29/2020.  Once police report is filed, she will share the photos and information about the theft with the team for their information.
  • Next meeting will be on March 10, 2020.  9:15a in the Fireside Room.

Like this post? Share it with your friends and family...

Facebook
Twitter
Pinterest

1 thought on “Construction Updates March 4”

Leave a Comment

Thank you FOR YOUR PLEDGE!

Because of you, we can continue to serve as a center of transformative love, faith and service!

Have questions or need to make changes?
Feel free to contact us, and we will be more than happy to answer all of your questions.